Acceptance items: Fire separation

Analysis of common problems at fire acceptance site - fire door 2

On-site problem description 4:

Steel fire door frame is not filled with cement mortar;

The steel fire-resistant window frames are not filled with cement mortar. In particular, you need to pay attention to whether the upper and lower frames of the fire-resistant doors and windows are filled in place.

Relevant specification requirements:

\”Code for Construction and Acceptance of Fireproof Roller Shutters, Fireproof Doors and Fireproof Windows\” GB50877—2014:

5.3.8 The door frame of steel fire doors should be filled with cement mortar. The door frame and the wall should be firmly connected with embedded steel parts or expansion bolts, and the distance between the fixed points should not be greater than 600mm.

5.4.2 The steel fireproof window frame should be filled with cement mortar. The window frame and the wall should be firmly connected with embedded steel parts or expansion bolts, and the distance between the fixed points should not be greater than 600mm.

Analysis of common problems at fire acceptance site - fire door 2

On-site problem description 5: The fire door does not have a permanent sign in an obvious location, or the sign is not comprehensive.

Relevant specification requirements:

\”Code for Construction and Acceptance of Fireproof Roller Shutters, Fireproof Doors and Fireproof Windows\” GB50877—2014:

4.3.2 Each orange fire door shall be equipped with a permanent sign on its visible part, and shall indicate the product name, model, specification, fire resistance and trademark, name and address of the production unit (manufacturer), and date of manufacture. And product production batch number, implementation standards, etc.

Analysis of common problems at fire acceptance site - fire door 2

On-site problem description 6:

The inclination angle of the outdoor evacuation stairs is greater than 45°, the evacuation door is facing the stairs;

Open doors, windows, and openings on the wall within 2m around the outdoor evacuation stairs.

Relevant specification requirements:

\”General Code for Building Fire Protection\” GB55037-2022:

7.1.11 Outdoor evacuation stairs shall comply with the following requirements:

1. The height of the handrails of outdoor evacuation stairs should not be less than 1.1m, and the inclination angle should not be greater than 45°;

2. Except for the outdoor evacuation stairs of buildings with 3 floors and below, which can be made of flame-retardant materials or wooden structures, the steps and platforms of the outdoor evacuation stairs are Non-combustible materials should be used;

3. Except for evacuation doors, there should be no other openings on the wall within 2 meters around the stairs, and the evacuation doors should not face the stairs.

\”Code for Fire Protection Design of Buildings\” GB50016-2014 (2018 Edition):

6.4.5 Outdoor evacuation stairs should comply with the following regulations:

3 , stairs and platforms should be made of non-combustible materials. The fire resistance limit of the platform should not be less than 1.00h, and the fire resistance limit of the stairs should not be less than 0.25h.

4. The door leading to the outdoor stairs should Use Class B fire doors and open outwards.

5. Except for evacuation doors, 2m around the stairs There should be no doors, windows or openings on the interior walls. Evacuation doors should not face stairs.

Analysis of common problems at fire acceptance site - fire door 2

On-site problem description 7:

Indoor rooms of residential buildings larger than 54m that are set up against exterior walls are not equipped with Class B fire doors as required by the design.

Related specification requirements: span>

\”Code for Fire Protection Design of Buildings\” GB50016-2014 (2018 Edition):

5.5.32 For residential buildings with a building height greater than 54m, each household should have one room that meets the following requirements:

1. It should be set up against the exterior wall, and the exterior window should be openable;

2. The fire resistance limit of the internal and external walls should not be less than 1.00h. The door of the room should be a Class B fire door. The fire resistance integrity of the exterior windows should not be less than 1.00h. .

Analysis of common problems at fire acceptance site - fire door 2

The pictures are from the Internet. If there is any infringement, please contact us to delete them.

Message at the end of the article:

Good-looking skins are all the same, but interesting souls are unique.

@bin马AYedu (firefighting) is walking with you, let’s be interesting together!

本站内容及图片来自网络,版权归原作者所有,内容仅供读者参考,不承担相关法律责任,如有侵犯请联系我们:609448834

(0)
华夏门网's avatar华夏门网
上一篇 2025年1月1日 09:23:45
下一篇 2025年1月1日 09:35:05

相关推荐

  • 2023年新国标防火门认证和验收介绍

    2023年新国标《GB12955防火门草案》的变化,从1991年第一版本到这次是防火门的第3版。新版本发布实施后,旧的版本就会宣布作废,通常实施日期会延后1年。咱们先来看下防火门有哪些变化: ①新版标准的防火门变化的第1项就是防火门增加了按场所分类的变化,分为:住宅入户防火门、疏散通道防火门、管道井检修防火门、其他应用场所防火门; ②旧版的按开启方向的分类取…

    防火门 2023年9月28日
    550
  • 开启防火门需要多大的力?

    发生火灾时,人们争相逃命,用夺门而出来形容应不为过;那么,防火门开启需要多大的力呢? 防火门关闭靠的是闭门器产生的力矩,闭门器的产生的力就是人们开启防火门所需要的力,我们来看看闭门器的力矩是多少? 根据规范《防火门闭门器》XF93-2004,各型闭门器开、关所需的力矩如下: 上图可以看出,防火门的开启力与门扇的质量、门扇的最大宽度有关,大家常见的主要有前三种…

    防火门 2024年3月9日
    1490
  • 锐亿科技取得一种方便观察的钢制防火门专利,通过特殊结构方便使用者进行观察

    金融界2024年5月30日消息,据国家知识产权局公告,浙江锐亿智能科技股份有限公司取得一项名为“一种方便观察的钢制防火门“,授权公告号CN221032283U,申请日期为2023年10月。 专利摘要显示,本实用新型公开了一种方便观察的钢制防火门,包括门框,所述门框的内侧对称设有防火门本体,所述防火门本体的正面设有探孔,所述探孔的内侧固定安装有玻璃板,所述探孔…

    防火门 2024年5月30日
    150
  • 安装医院钢制防火门的注意事项有哪些?

    医院钢制防火门不仅仅是一个直观的装饰,更是可以延续生命流逝的守护神,所以如何准确的安装防火门是非常关键的,准确的安装方法可以使其发挥作用,上面之中沃防火门为大家介绍一下安装防火门的流程和注意事项。 一、防火门的安装过程。 1. 安装之初,要根据设计要求的尺寸和主峰方向,画出门框的位置线。安装防火门时,应根据防火门的类型采用相应的安装方法。。 2. 安装防火门…

    防火门 2024年2月18日
    70
  • 如何正确选择防火门

    《如何正确选择防火门》 防火门在建筑物的消防安全中起着至关重要的作用,它能够有效延缓火势蔓延,为人员疏散争取宝贵时间。然而,面对市场上众多的防火门产品,我们应该如何做出正确的选择呢? 首先,要明确防火等级需求。防火门根据耐火性能分为不同的等级,如甲级、乙级、丙级等。不同等级的防火门在耐火时间上有所差异。在选择时,需根据建筑物的类型、用途以及消防安全要求来确定…

    防火门 2024年6月8日
    140

联系我们

400-800-8888

在线咨询: QQ交谈

邮件:[email protected]

工作时间:周一至周五,9:30-18:30,节假日休息

关注微信