For the first decoration, the correct process and order are here! Hope to give you some help

Many friends who are decorated for the first time, what should be dazed for the decoration, so that the construction period is prolonged, the cost is increased, what the cost is increased, I don’t know what to know. You can only stay in …

For the first decoration, the correct process and order are here! Hope to give you some help <p class =\" pgc-cappion \"

Let me introduce the correct decoration process and order today, so that everyone can quickly install a texture home ~

For the first decoration, the correct process and order are here! Hope to give you some help

Before officially started

1st step: Clarifying living needs

Family residential population, storage, entertainment space needs, home style and future of the future Life planning (such as two babies) and so on. notB: gif.jpeg? _iz = 58558 & from = Article.pc_detail & LK3S = 953192F4 & X-EXPIRES = 1739324563 & SIGNATURE = 76xuoosxdul7E5GSGINWCHMTWBC% 3d \”/>

Step 2: Prepare the decoration budget

Prepare the budget:

For the first decoration, the correct process and order are here! Hope to give you some help

Half-bag 6w

For the first decoration, the correct process and order are here! Hope to give you some help

</

Half-bag 7w

For the first decoration, the correct process and order are here! Hope to give you some help

Half-bag 8W

half-bag 9W

Half-bag 11w

half -bag 12W

Suggestion: decoration fee, furniture fee, home appliance fee is divided by 2: 2: 1. text-align: left; \”data-track =\” 28 \”> Step 3: Determine the decoration method

mainstream decoration method There are three types, all-inclusive, half-bag, and clear bags. The differences are as follows:

For the first decoration, the correct process and order are here! Hope to give you some help

Suggestion:

    <li style =\" text-align: left; All-inclusive;
  • I have time but cannot track the decoration throughout the process, choose a half package;
  • In full time and rich decoration experience, choose a clear package.

Step 4: Choose the decoration company

After determining the decoration method, we must also find a reliable decoration company to decorate .

For the first decoration, the correct process and order are here! Hope to give you some help

Suggestion:

  • Pursuing home quality can find design decoration companies;
  • If you do not design or design yourself, you have time but have limited economic capabilities, choose the construction team;
  • <li style = \"text-align: left; Ordinary decoration company.

For the first decoration, the correct process and order are here! Hope to give you some help

Step 5: Confirm the design plan and sign the contract

This is usually like this (such as Feimo Family):

For the first decoration, the correct process and order are here! Hope to give you some help

Communication design → pay the house fee house → out of the graphic design drawing and overall cost → design fee design renderings → design Wolved to satisfaction → sign the construction contract, and pay the construction fee in proportion. web: gif .jpeg? _IZ = 58558 & from = Article.pc_detail & LK3S = 953192F4 & X-EXPIRES = 1739324563 & X-Signature = Zo7kovyk5hm66Kdujqxhrllwf4 3D 3D 3D 3D 3D \”/>

△ Graphic design diagram

△ Design renderings

p> For the first decoration, the correct process and order are here! Hope to give you some help

In the hard installation construction

The first step: Starting the bottom

On the day of the construction, the owner, designer, project manager ( The three parties were present to check and confirm the overall design and transformation. gif .jpeg? _iz = 58558 & from = Article.pc_detail & LK3S = 953192F4 & X-EXP IRS = 1739324563 & SIGNATURE = ZALMNS6R2FGYN5%2Be0jvig%3 D \”/>

Step 2: Protection before starting

Out of finished products, such as household door, window, water pipe, meter box, gas meter, etc. TT-Origin-Web: GIF.JPEG? _IZ = 58558 & From = Article.pc_detail & LK3S = 953192F4 & X-EXPIRES = 1739324563 & X-Signature = 5DAMPZF5BNVYH7KX2CAG7EKDBY%3D \”/>

Especially for parts For the reconstructed hardcover room, we must take perfect protection measures before construction. img src = \”https://p3-sign.toutiaoimg.com/pgc- Image/61A30FC01DC0477A86927F2594CCF~tplv- origin-jpeg?_iz=58558 &FROM = Article.pc_detail & LK3S = 953192F4 & X-EXPIRES = 1739324563 & X-Signature = Lqlswze7ajaehiwnbhypmk5lvyc%3d \”/>

Step 3: /p>

Demolition and newly built local walls according to the design scheme, it must be built first and then built:

① Disassembling process: Positioning → Cutting along the line → Demolition → Packing and Clearing → Sorting the site

For the first decoration, the correct process and order are here! Hope to give you some help

Note:

  • Loire bearing beam, column, padded surface (flat layer) forbidation.
  • Public facilities (flue, main drainage pipes, gas pipelines, fire protection equipment) forbid demolition. Disassembly is prohibited from opening the door and windows, demolition involving heat insulation and waterproofing.
  • The bearing wall is prohibited from dismantling. .tiaoimg.com/pgc- Image/DBFABF8CC4C4C47A0F0D6CBADE37173 ~ TPLV-Origin-WEB: GIF.JPEG? = 953192F4 & X-EXPIRES = 1739324563 & X-Signature = AAQYMJT7FUGRDB7ZURA6KWFZ22K%3d \”/>

    New process: Positioning → Basic beam → moisturizing → planting walls → cap → ceiling → ceiling → ceiling → cap → Hanging net painting → Cleaning → Maintenance

    Step 4: Hydropower transformation

    The whole house is up and down, and the transformation of a strong and weak circuit.

    Specific process:

    Hydropower base → hydropower estimation → material entry → putting wire slot → strong and weak electric fabric tube → giving water drainage tube → strong electric box finishing → on -site cleanup → project self -inspection → acceptance

    For the first decoration, the correct process and order are here! Hope to give you some help

    Note:

    ① Determine whether to install the central air conditioner, fresh air system, floor heating/heating tablet;

    ② planning the planning of all electrical appliances, bathroom sanitary ware, hot water circulation systems in the house, the location of the socket, and the number of lamps positions , Prevent dimensional errors or omissions in the later period.

    For the first decoration, the correct process and order are here! Hope to give you some help

    Step 5: mud tile construction

    Specific procedures:

    Paying pipeline construction → wall layer treatment → painting wall waterproof → paving wall tiles → painting Waterproof → closed water test → paving floor tiles → cleaning protection → marking signs

    Note:

    <p style = \"text-align: left; , Floor tiles, threshold stones, and confirm the paving method.

    ② the corners of the floor tiles and wall tiles must be protected to avoid bumps in the later construction.

    For the first decoration, the correct process and order are here! Hope to give you some help

    Step 6 : Woodworking construction

    Including ceilings, curtain boxes, cabinets, indoor doors, door sleeves, card seats, beds, wooden jewelry grassroots and other projects.

    For the first decoration, the correct process and order are here! Hope to give you some help

    Among them, different Projects, different construction processes:

    • Ceiling: Put the line → punch → install a keel → make production → production Curtain box → Make the air outlet → the keel hidden acceptance → install gypsum board
    • <li style = \"text-align: left; Counterplane → Sealing

    • Wall wooden grassroots: Put on the line → install the grass-roots keel → make the grassroots level level → Annan Decorative panel
    • Cabinet: Positioning the bomb line → punching → making cabinets → check-in → assembly fixation → installation hardware </
    • Door panel: prepare cutting board → select the decorative panel → press the border → the side → clean the door → install and debug
    • Pot: Pole down the wooden wedge → tailoring → moisture processed → installation of the layer → installing the edge </</

    For the first decoration, the correct process and order are here! Hope to give you some help

    >

    Note:

    If you create a cabinet and indoor door on the spot, you need to buy various hardware accessories in advance. >

    Wood production such as walls, cabinets, and the construction of late-surface latex paint. p3- sign.toutiaoimg.com/pgc- Image/7B2468F0E457FB4998A27BD6022F4~TPLV-Origin-web:gif.jpeg?_iz=5558&FROM=Article.pc_detail p lk3s = 953192F4 & X-EXPIRES = 1739324563 & X-Signature = B%2BSYEHGYH0E536%2BYLE2TDS1GD%2BQ% 3d \”/>

    Construction process:

    Wall Test → Brush the interface agent → the grassroots leveling → hanging grid cloth → batch scraping putty → painting primer → painting with paint </

    Note:

    • Before brushing paint, protect the remaining finished products that have been completed to prevent pollution.data-track = \”156\”> rainy weather is not suitable for paint work.
    • The paint on the wall should be painted once and twice.
    • When working on wooden paint, it is necessary to wrap the hardware to prevent pollution.

    For the first decoration, the correct process and order are here! Hope to give you some help

    After the hard installation is completed

    After the hard installation is over, various installation projects have successively entered the field:

    ① wall tiles and brick sewing (you can be scheduled to buy after the muddy is over)

    ② Switch socket and lamp installation (orbit lights, lamp bands and other embedded lamps need to be purchased and installed in the stages of woodworking; = \”https://p26-sign.toutiaoimg.com/pgc- Image/4889fceb0d7DEA272722B11030C0314~tplv- origin-eb:gif.jpeg?_iz=58558&From=arti Cle.pc_detail & lk3s = 953192F4 & X-EXPIRES = 1739324563 & X-Signature = 35CF% 2bpcjf5z1hqmxcy7fn3i2iag%3d \”/>

    ③ Wooden floor+skirting line installation (select the color in the design phase, buy it at the latest after hard installation)

    ④ Kitchen and bathroom integrated ceiling installation (you can be preserved after the mud workers can be preserved)

    ⑤ Cabinet and custom cabinet installation (the water circuit diagram of the cabinet must be first tested before the water and electricity starts, and the size of the re-test is completed at the end of the mudman; the construction period is about 30-45 days) https://p3-sign.toutiaoimg.com/pgc- Image/3AB060C7D3074196971CBB47B77E1CBD~ TPLV- Origin-web:gif.jpeg?_IZ= 5858&From=article.p C_Detail & LK3S = 953192F4 & X-EXPIRES = 1739324563 & X-Signature = Gzaesr%2Baok23Y1C04E% 2bgl64n2as%3d \”/>

    ⑥ Form electrical and bathroom cleansing must be confirmed in hydropower stages)

    <p style = \"text-align: left; The carpentry stage measurement and purchase, the construction period is about 15-30 days)

    <p style = \"text-align: left; , About 7-15 days)

    For the first decoration, the correct process and order are here! Hope to give you some help

    After the installation project is over, there are various soft furniture and accessories of sofas, beds and other soft furniture and accessories. At this point, the decoration will come to an end, and then ventilate for 3-6 months. After the indoor air quality is reached, you can check in. src = \”https://p3-sign.toutiaoimg.com/pgc- Image/d3C95B7B04b84752B90A12F081F0C4~tplv- origin-web:gif.jpeg?_iz=58558 &From=ar TICLE.PC_Detail & LK3S = 953192F4 & X-EXPIRES = 1739324563 & X-Signature =% 2FTF%2F%2bbop4V%2F4BACEZNDCMKJ%2BZZE%3d \”/>

    > 189\”>> 189 \”>> 189\”>> 189 \”>> 189\”>> 189 \”>> 189\”> This is the correct order of the decoration. I wish everyone can decorate smoothly and live in a new home as soon as possible ~

    (PS: Some pictures are derived from the Internet. If infringement, please contact delete.)

    <p style = \"text-align: left; Choose

    本站内容及图片来自网络,版权归原作者所有,内容仅供读者参考,不承担相关法律责任,如有侵犯请联系我们:609448834

Like (0)
华夏门网的头像华夏门网
Previous 2025年2月5日
Next 2025年2月5日

相关推荐

联系我们

400-800-8888

在线咨询: QQ交谈

邮件:[email protected]

工作时间:周一至周五,9:30-18:30,节假日休息

关注微信