Construction safety knowledge points for the registered safety engineer examination – formwork installation and removal

The template construction and installation should comply with the following regulations:

(1) The formwork installation should be assembled in the order of the design and construction instructions. Support columns such as wooden poles, steel pipes, and door frames must not be mixed.

(2) When the vertical formwork and support column support parts are installed on the base soil,backing plates should be added The backing plate should have sufficient strength and supporting area, and should be centrally loaded. The base soil should be solid and there should be drainage measures. Waterproofing measures should be taken for collapsible loess; for particularly important structural projects, concrete, piling and other measures can be used to prevent the support columns from sinking. Measures should be taken to prevent frost-heaving soil from freezing and thawing.

Construction safety knowledge points for the registered safety engineer examination - formwork installation and removal

(3) During the installation process of the template and its bracket, effective prevention must be set Overturned temporary fixtures.

(4) For cast-in-place reinforced concrete beams and slabs, when the span is greater than 4m, the formwork should Arching; When there are no specific requirements in the design, the arching height should be 1/ 1000~3/ 1000 of the full span length.

(5) For cast-in-situ multi-story or high-rise houses and structures, the installation of upper formwork and its brackets should comply with the following regulations: Lower floor slab It should be able to withstand the construction load of the upper layer.load capacity, otherwise support brackets should be added;The upper bracket columns should be aligned with the lower bracket columns, and pads should be laid at the bottom of the columns; When the cantilever hanging formwork and truss formwork methods are used, the support structure The load-bearing capacity and stiffness must meet the design and construction requirements. (6) When the inter-story height> 5m, truss formwork or steel pipe column formwork should be used. When the inter-layer height ≤ 5m, wooden columns can be used to support formwork.

Construction safety knowledge points for the registered safety engineer examination - formwork installation and removal

When assembling vertical formwork with a height of more than 2m, you are not allowed to stand on the lower formwork Assemble the upper template. Temporary fixed facilities should be set up during installation.

The structure and installation of bracket columns supporting beams and plates should comply with the following regulations: (1) The vertical and horizontal columns of beams and plates should be The spacing should be equal or multiple. (2) Wooden posts should be set with pads at the bottom and support heads at the top. The steel pipe columns should be provided with pads and bases at the bottom, and adjustable supports should be provided at the top. The screw rod shall not protrude from the top of the steel pipe by more than 200mm. (3) At a height of 200mm from the bottom of the column to the ground, sweep poles should be installed in the vertical, horizontal and horizontal directions according to the vertical and horizontal procedures.

When the floor height is 8~20m, at the top step strong>A horizontal pull shouldbe added between the two horizontal tie rodsRods; When the floor heightis greater than 20m, a horizontal tie rod should be added between the top two steps of the horizontal tie rods.

Construction safety knowledge points for the registered safety engineer examination - formwork installation and removal

The removal period of the formwork should comply with the following regulations:

① The non-load-bearing side formwork should be used only when the strength of the concrete can ensure that its surface and edges will not be damaged by removing the formwork. Dismantling, the dismantling time should be 12 hours later.

②The load-bearing formwork can only be removed after the concrete strength meets the requirements in the table below.

Component type

Member span/m

Achieve the designed compression resistance of the concrete cube Percentage of intensity standard value/%

Board

≤2

≥50

>2,≤8

≥75

>8

≥100

(2) In addition to meeting the concrete strength requirements, the form removal time for large-volume concrete should also ensure that the temperature difference between the inside and outside of the concrete drops below 25°C. Otherwise, effective measures should be taken to prevent temperature cracks from occurring.

(3) Before removing the mold, check that the tools used are effective and reliable. Wrenches and other tools must be put into tool bags or systems. Hang it on your body and check the safety measures within the mold removal site.

(4) The dismantling work of the formwork should be directed by a dedicated person. The work area should be fenced, no other types of work should be allowed within it, and a dedicated person should be assigned to monitor it. It is strictly prohibited to throw the removed templates and spare parts.

Construction safety knowledge points for the registered safety engineer examination - formwork installation and removal

(5) The order and method of formwork removal should be carried out according to the design regulations of the formwork. When there is no provision in the design, the first support can be removed first, and the rear support can be removed first. Non-load-bearing formwork should be dismantled from top to bottom. The removed formwork should not be thrown away and should be stacked in designated locations.

(6) When dismantling formwork at high places, regulations on high-altitude operations should be followed. It is strictly prohibited to use sledgehammers and crowbars. The temporarily removed formwork on the operating level should not be stacked more than 3 layers. .

(7) The structure where the formwork has been removed can bear all the design load only after the concrete strength reaches the design strength value. If it is necessary to add construction load to the structure before the design strength is reached. , should be calculated separately, and if the strength is insufficient, temporary supports should be added.

本站内容及图片来自网络,版权归原作者所有,内容仅供读者参考,不承担相关法律责任,如有侵犯请联系我们:609448834

Like (0)
华夏门网的头像华夏门网
Previous 2025年1月19日
Next 2025年1月19日

相关推荐

  • Check in for two years! Should developers change the door window? My real experience tells you

    When the year is approaching, a wave of delivery is coming soon, and many people are considering how to decorate new houses. Today I will talk about a topic that everyone is partic…

    门窗安装 2025年2月17日
    70
  • 门窗十大品牌2023排行榜

    在2023年,各大门窗品牌为争夺市场份额,不断推陈出新,竞争激烈。为了帮助消费者更好地了解当前市场,我们将这些门窗品牌根据品牌价值、口碑评价等多项指数评选出了2023年门窗十大品牌排行榜。 1.阿尔卑斯门窗 阿尔卑斯门窗是具有较高知名度的门窗品牌,以高质量、高性能的产品在市场上赢得了良好的声誉。 2.富轩门窗 总部坐落于佛山市南海区的富轩全屋门窗,自创立以来…

    门窗安装 2024年2月5日
    130
  • 装一扇好门,给幸福生活多增添一份保障

    理想的家是什么样?从来没有固定标准,但应该包含一切热爱的东西,蕴含你对生活的理解和感悟,足以让你在任何时候放松和安静。 我想有个家,一个洒满阳光,可以容纳闲适心境的生活空间。理想的家居,搭配适宜的门,惬意的生活,那就从装一樘欧华尊邸铸铝门开始吧。 1、品质,不可少 坚持、专注、创新,无论外界环境如何变化,欧华尊邸铸铝门对自己做的事情有着高度的坚守。我们坚持不…

    门窗安装 2023年9月19日
    100
  • 空调拆机过程与步骤

    空调拆机过程与步骤 步骤一:准备工作 在拆卸空调之前,必须确保以下准备工作已经完成: 【专业师傅快速上门,专业服务有保障】 (此处已添加小程序,请到今日头条客户端查看) 确保安全:在进行任何维修工作之前,确保空调已经断开电源,并且工作环境安全无隐患。 准备工具:准备好所需的工具,如螺丝刀、扳手、钳子等,以便拆卸及维修空调。 资料获取:查找并准备好空调的拆机说…

    门窗安装 2024年5月26日
    180
  • 掌握深度学习技术的十个步骤

    掌握深度学习:从零到精通的十个步骤 深度学习是人工智能领域中最热门、最具前景的分支之一。它利用神经网络模型来模拟人类大脑的学习过程,从而在图像识别、语音识别、自然语言处理、推荐系统等众多领域取得了突破性的成果。掌握深度学习技术对于想要在人工智能领域取得成功的人来说是至关重要的。 以下是掌握深度学习技术的十个步骤: 一、了解深度学习的基本概念 深度学习是机器学…

    门窗安装 2023年12月18日
    100

联系我们

400-800-8888

在线咨询: QQ交谈

邮件:[email protected]

工作时间:周一至周五,9:30-18:30,节假日休息

关注微信