Construction safety knowledge points for the registered safety engineer examination – formwork installation and removal

The template construction and installation should comply with the following regulations:

(1) The formwork installation should be assembled in the order of the design and construction instructions. Support columns such as wooden poles, steel pipes, and door frames must not be mixed.

(2) When the vertical formwork and support column support parts are installed on the base soil,backing plates should be added The backing plate should have sufficient strength and supporting area, and should be centrally loaded. The base soil should be solid and there should be drainage measures. Waterproofing measures should be taken for collapsible loess; for particularly important structural projects, concrete, piling and other measures can be used to prevent the support columns from sinking. Measures should be taken to prevent frost-heaving soil from freezing and thawing.

Construction safety knowledge points for the registered safety engineer examination - formwork installation and removal

(3) During the installation process of the template and its bracket, effective prevention must be set Overturned temporary fixtures.

(4) For cast-in-place reinforced concrete beams and slabs, when the span is greater than 4m, the formwork should Arching; When there are no specific requirements in the design, the arching height should be 1/ 1000~3/ 1000 of the full span length.

(5) For cast-in-situ multi-story or high-rise houses and structures, the installation of upper formwork and its brackets should comply with the following regulations: Lower floor slab It should be able to withstand the construction load of the upper layer.load capacity, otherwise support brackets should be added;The upper bracket columns should be aligned with the lower bracket columns, and pads should be laid at the bottom of the columns; When the cantilever hanging formwork and truss formwork methods are used, the support structure The load-bearing capacity and stiffness must meet the design and construction requirements. (6) When the inter-story height> 5m, truss formwork or steel pipe column formwork should be used. When the inter-layer height ≤ 5m, wooden columns can be used to support formwork.

Construction safety knowledge points for the registered safety engineer examination - formwork installation and removal

When assembling vertical formwork with a height of more than 2m, you are not allowed to stand on the lower formwork Assemble the upper template. Temporary fixed facilities should be set up during installation.

The structure and installation of bracket columns supporting beams and plates should comply with the following regulations: (1) The vertical and horizontal columns of beams and plates should be The spacing should be equal or multiple. (2) Wooden posts should be set with pads at the bottom and support heads at the top. The steel pipe columns should be provided with pads and bases at the bottom, and adjustable supports should be provided at the top. The screw rod shall not protrude from the top of the steel pipe by more than 200mm. (3) At a height of 200mm from the bottom of the column to the ground, sweep poles should be installed in the vertical, horizontal and horizontal directions according to the vertical and horizontal procedures.

When the floor height is 8~20m, at the top step strong>A horizontal pull shouldbe added between the two horizontal tie rodsRods; When the floor heightis greater than 20m, a horizontal tie rod should be added between the top two steps of the horizontal tie rods.

Construction safety knowledge points for the registered safety engineer examination - formwork installation and removal

The removal period of the formwork should comply with the following regulations:

① The non-load-bearing side formwork should be used only when the strength of the concrete can ensure that its surface and edges will not be damaged by removing the formwork. Dismantling, the dismantling time should be 12 hours later.

②The load-bearing formwork can only be removed after the concrete strength meets the requirements in the table below.

Component type

Member span/m

Achieve the designed compression resistance of the concrete cube Percentage of intensity standard value/%

Board

≤2

≥50

>2,≤8

≥75

>8

≥100

(2) In addition to meeting the concrete strength requirements, the form removal time for large-volume concrete should also ensure that the temperature difference between the inside and outside of the concrete drops below 25°C. Otherwise, effective measures should be taken to prevent temperature cracks from occurring.

(3) Before removing the mold, check that the tools used are effective and reliable. Wrenches and other tools must be put into tool bags or systems. Hang it on your body and check the safety measures within the mold removal site.

(4) The dismantling work of the formwork should be directed by a dedicated person. The work area should be fenced, no other types of work should be allowed within it, and a dedicated person should be assigned to monitor it. It is strictly prohibited to throw the removed templates and spare parts.

Construction safety knowledge points for the registered safety engineer examination - formwork installation and removal

(5) The order and method of formwork removal should be carried out according to the design regulations of the formwork. When there is no provision in the design, the first support can be removed first, and the rear support can be removed first. Non-load-bearing formwork should be dismantled from top to bottom. The removed formwork should not be thrown away and should be stacked in designated locations.

(6) When dismantling formwork at high places, regulations on high-altitude operations should be followed. It is strictly prohibited to use sledgehammers and crowbars. The temporarily removed formwork on the operating level should not be stacked more than 3 layers. .

(7) The structure where the formwork has been removed can bear all the design load only after the concrete strength reaches the design strength value. If it is necessary to add construction load to the structure before the design strength is reached. , should be calculated separately, and if the strength is insufficient, temporary supports should be added.

本站内容及图片来自网络,版权归原作者所有,内容仅供读者参考,不承担相关法律责任,如有侵犯请联系我们:609448834

Like (0)
华夏门网的头像华夏门网
Previous 2025年1月19日
Next 2025年1月19日

相关推荐

  • 如何减少AI“一本正经地胡诌”?新方法出现了

    新研究:新技术助力人工智能减少“胡诌” 人工智能(AI)中广泛使用的大语言模型不时出现的“一本正经地胡诌”是其难以克服的问题。近日,英国牛津大学研究团队开发出一种名为“语义熵”的新方法,有望大幅提升AI回答的可靠性。 大语言模型的“胡诌”在业界被称为“幻觉”,牛津大学计算机科学系的研究人员提出“语义熵”方法试图解决这一问题。在热力学中,熵描述的是系统的混乱或…

    门窗安装 2024年7月19日
    50
  • 武汉铝艺大门安装

    武汉铝艺大门安装圆满完成 近日,在武汉市江汉区一处小区内,一道华丽的铝艺大门吸引了众人的目光。 据悉,这道大门是由武汉市的铝艺制品承制并安装,经过数天的精心施工,终于圆满完成。 据该负责人介绍,这道铝艺大门采用高强度铝合金材料制作,通过精密的数控加工和高温喷涂处理,使得大门表面呈现出金属质感和珍珠光泽的结合。 同时,该大门还配备了智能感应系统和远程控制器,方…

    门窗安装 2023年10月31日
    140
  • Brand list of the top ten brands of doors and windows in 2025

    Doors and windows are an important part of home decoration, and the choice of their brand is crucial. In 2025, competition in the doors and windows industry is fierce, and many bra…

    门窗安装 2024年12月25日
    50
  • 2024十大门窗品牌最新排名

    在门窗的世界里,有众多优秀的品牌闪耀着独特的光芒。让我们一同走进十大门窗品牌的精彩天地。 斯卡特门窗,以其无可挑剔的品质和引领潮流的设计,成为行业的标杆。每一扇门窗都仿佛是一件艺术品,展现出极致的魅力。 皇派门窗,其凭借着精湛的工艺和出色的性能,为无数家庭带来了安心与舒适,深受消费者的赞誉。 良木道门窗,它以创新为动力,不断推出令人惊艳的产品,在门窗领域开辟…

    门窗安装 2024年6月11日
    190
  • 小小的门窗安装,大大的建筑知识

    1、门窗框安装工作应在室内、外抹灰找平、刮糙等湿作业完毕后进行。 2、弹线:首先应弹出门窗洞中的中心线,从中心线确定基准洞口宽度,门窗框安装后,应与墙面阳角线尺寸保持一致。在洞口两侧弹出同一标高的水平线,且水平线在同一楼层内标高均应相同。 3、门窗框安装:按照弹线位置,将门窗框临时用木楔固定,用水平尺和托线板反复校正门窗框的垂直度及水平度,并调整木楔直至门窗…

    门窗安装 2023年12月19日
    60

联系我们

400-800-8888

在线咨询: QQ交谈

邮件:[email protected]

工作时间:周一至周五,9:30-18:30,节假日休息

关注微信