The decoration process sequence and precautions are completely organized! (recommended collection)

Decoration is an endless subject that ordinary people only experience once in a lifetime When it comes to decoration, we definitely don’t have experience. We can only avoid pitfalls in our own decoration by learning from other people’s experiences. However, decoration is a long-term and complicated process. The design sister once personally renovated a house of her own, and participated in everything from design to moving bricks. This was an experience I will never forget. During the nearly one-year renovation process, I also wrote a lot of renovation diaries and summarized a lot of experience. Here is a summary of the renovation process and precautions for your reference.

The decoration process sequence and precautions are completely organized! (recommended collection)

1. Summary of decoration process:

Design plan – demolition of walls

——Water and electricity renovation-central air conditioning-window sealing and replacement

——Tiling – suspended ceiling – replacing the door

——Wall putty and paint – interior door installation – cabinet installation

——Range hoods and stoves—custom cabinet installation—wallpaper and wall coverings—wooden floors—switches and sockets—lighting installation—bathroom hardware—curtains, hanging paintings

——Paint touch-up-cleaning-furniture and appliances.

Note: Some processes with the same font color can be crossed simultaneously.

2. Precautions for each decoration process

① Design plan and demolition of walls

If the decoration budget is sufficient, it is recommended to find a designer to make a complete decoration design plan. In this way, the decoration is equivalent to having an extra military person who can strategize. For more information about the benefits of designers, you can refer to reading \”Should I hire a designer for decoration?\” Only those who have hired a designer will know these 6 benefits\”

The decoration process sequence and precautions are completely organized! (recommended collection)

Demolition requires clean demolition and protection of projects that will not be demolished; while building walls, the main considerations are to prevent wall cracking, the connection between the old and new walls, the lintel technology, and the sloping brick capping. For details, please refer to my decoration diary \”Are you afraid of uneven tiles when laying tiles?\” Learn about the details and precautions of the tiling process丨Decoration Diary》.

The decoration process sequence and precautions are completely organized! (recommended collection)

② Water and electricity renovation, central air conditioning and window sealing

In terms of water and electricity renovation, it is recommended that the kitchen water and electricity diagram be obtained from custom cabinets in advance. In terms of craftsmanship, attention should be paid to: loose line technology, water pipe suppression, waterproof and closed water test, dedicated line for air conditioning, weak current layout, kitchen refrigerator circuit Leave it alone, leave switches for kitchen appliances, The wall-mounted TV sockets are located in the upper left and right corners of the TV. For details, please refer to \”Plumbing Precautions | Decoration Diary\” and \”Bathroom Waterproofing and Secondary Drainage Precautions | Decoration Diary\”. When sealing windows, pay attention to waterproofing.

The decoration process sequence and precautions are completely organized! (recommended collection)

③tiles, ceilings and doors

In terms of tiling, you need to pay attention to: soaking the tiles in water, processing of the yin and yang corners, pressing the bathroom wall to the floor, and splicing wood grain tiles , the size of the gap, the fullness of the mortar, and the dry hanging of large bricks. For details, please refer to \”Afraid of Uneven Bricks When Tiling?\”Learn about the artistic details and precautions in Decoration Diary.

The decoration process sequence and precautions are completely organized! (recommended collection)

As for the suspended ceiling, matters needing attention include: light steel keel and wooden keel, anti-cracking process, yin and yang corner treatment, nail hole anti-rust, connection with water, electricity or central air conditioning and other equipment. For details, please refer to \”Doing Thanks to these craftsmanship details, the ceiling will never crack again! (Decoration Diary)\”.

The decoration process sequence and precautions are completely organized! (recommended collection)

Because when replacing the door, dismantling and installing the door will involve a relatively large movement. It is generally recommended to replace the door and threshold stone after the tiling is completed. After the door is replaced, the putty can be patched to facilitate painting. Work entry and exit connection.

④Walls, interior doors and cabinets

Wall construction is after the wall tiles and floor tiles are completed. During construction, you need to pay attention to the following: ground protection, checking for hollows, leveling, solidifying old walls, drying putty before construction, and protecting sun corners. For details on the construction techniques of color-blocked walls and blackboard walls, please refer to \”Wall Construction丨What should I pay attention to when scraping putty and painting?\” (Decoration Diary)\”.

The decoration process sequence and precautions are completely organized! (recommended collection)

Then the indoor door is installed. It is recommended to complete the first coat of topcoat so that the closing is more perfect. For details, please refer to \”Wooden Door Installation and Purchase Precautions, and by the way, plant a stunning door丨Decoration Diary\” .

The decoration process sequence and precautions are completely organized! (recommended collection)

Then in terms of cabinet customization, although the installation is in comparison Later, because the water and electricity renovation requires the custom cabinet manufacturer to provide the kitchen water and electricity diagram, so the cabinet merchant must confirm it before the renovation! The cabinet merchant must be determined before decoration! The cabinet merchant must be determined before decoration!

⑤Oil stove, cabinet, wall covering, wooden floor and finishing touches

The range hood and stove must be combined with the cabinet, so the style of the stove must be selected before the cabinet plan is determined so that the dimensions can be reserved for the cabinet design.

The decoration process sequence and precautions are completely organized! (recommended collection)

As for the installation of custom cabinets, the construction connection between wallpaper and wooden floors, the main thing is to finish the details. For example, a closing strip should be used between the wooden floor and the cabinet, and between the cabinet and the wall covering, it is recommended that the wall covering be tucked into the cabinet and skirting to prevent the edges of the wall covering from being exposed.

The decoration process sequence and precautions are completely organized! (recommended collection)

Then comes the final installation work of switches and sockets, lamps, bathroom hardware, curtains and paintings, etc.

⑥Cleaning, furniture appliances and touch-up paint

Finally, I need to remind you that although the wall paint has been painted at the end of the decoration, there may be problems in the later stages of wooden floors, custom cabinets, hanging paintings, moving furniture, and air-conditioning installation. It will collide with the painted wall, so it is recommended to keep the remaining latex paint after the hard decoration is completed, so that all decorations, furniture and appliances can be repainted regularly.

The decoration process sequence and precautions are completely organized! (recommended collection)

At this point, the decoration should be almost complete. I guess you are already exhausted physically and mentally, and at the same time, you are full of expectations for your new home. . However, if you are still reading the article at this time, I am afraid you are still in the early stage of decoration. There are many pitfalls in the design, construction and material selection during the decoration process waiting for you to overcome. If you want to avoid pitfalls during decoration, you may wish to follow me, I will do it every day. Share some practical knowledge on decoration!

本站内容及图片来自网络,版权归原作者所有,内容仅供读者参考,不承担相关法律责任,如有侵犯请联系我们:609448834

(0)
华夏门网's avatar华夏门网
上一篇 2024年12月27日 09:05:40
下一篇 2024年12月27日 09:07:56

相关推荐

  • 有用收藏!这些家居的最佳尺寸你知道吗?

    切菜时腰酸背疼,睡觉时噩梦连连,开灯后光线刺眼…你想过吗,这可能是家具尺寸及摆放出了问题。 家居装饰中,大到沙发、床,小到枕头、灯具,都有最佳尺寸与摆放距离,即使与标准仅差几厘米,也会悄悄损害健康。桌椅高度差多少合适?衣柜多高最好用?戳图参考↓ 来源:生命时报

    门业资讯 2024年6月10日
    930
  • 2023家居微观察年度榜单之“十大改变”!

    变则通,通则存,存则强。 ——《周易·系辞下传》 2023年是充满变化的一年,随着房地产高速增长的时代已经过去,家居市场的发展也正在从量的扩张转向质的提升。从品类到战略、从业务到模式、从宏观政策到消费市场,都在“变”中暗藏机遇与风险。 站在未来看现在,2023家居微观察年度榜单之“十大改变”重大来袭,与大家共同探讨、寻找隐藏在发展与变化中的机会。 1、政策之…

    门业资讯 2024年2月10日
    170
  • 家居装修全攻略:实用技巧打造美观舒适家

    大家好,我是一名专注于家居装饰领域的资深内容创作者。 在这个快节奏的时代,人们越来越注重居住环境的舒适和美观。 新房装修成为了每个家庭关注的焦点。 在装修过程中,如何合理规划空间、选择材料以及避免常见问题成为了大家热议的话题。 在我的亲身经历中,我发现很多人在选择装修风格时往往盲目跟风,没有考虑到自己的实际需求和个人喜好。 因此,我的第一个建议是,在装修之前…

    门业资讯 2024年6月19日
    100
  • From rough to stunning: 116㎡ modern cream style, comparison before and after decoration costing RMB 260,000

    From rough to stunning: 116㎡ modern cream style, comparison before and after decoration of RMB 260,000 The principle of rough decoration is to \”make it bigger, brighter and …

    门业资讯 2025年1月7日
    500
  • Up to 30,000 yuan! Renovation subsidy is here

    On February 15, the Nanjing Municipal Housing Security and Real Estate Bureau issued a statementYu Jiali\’s announcement on the application for purchase subsidies for items a…

    门业资讯 2025年2月16日
    180

联系我们

400-800-8888

在线咨询: QQ交谈

邮件:[email protected]

工作时间:周一至周五,9:30-18:30,节假日休息

关注微信